Dubai Defects Liability Period: 1 Year or 10?

Writer: RAMI
RAMI
Nov 19
5 min read

Under Dubai Law No. 6 of 2019, a developer's liability for defects runs on two different clocks. Structural defects — problems with the foundation, columns, beams, slabs, or load-bearing walls — are covered for ten years from the date the project's completion certificate is issued. Non-structural defects in mechanical, electrical, plumbing, and drainage installations are covered for just one year, counted from the date the unit is handed over to the owner (or from the completion certificate if the owner delays taking possession). Both periods are legal minimums; a sale agreement clause that shortens them is void. In practice, the one-year window matters most to new owners, because it covers the electrical sockets, water leaks, and AC issues a snagging inspection is most likely to catch — and that clock starts the day you collect your keys.


At RAMI Property Inspections & Snagging, Dubai's property inspection and snagging company, we see buyers confuse these two windows constantly — assuming the headline "ten-year warranty" covers everything, then missing the one-year deadline for the issues that actually show up first.


Two Clocks, Two Very Different Defects

The confusion is understandable. Developers and agents often talk about "the warranty" as if it's one single period. Legally, it's two, and they don't run on the same calendar or cover the same things.


Aspect

Structural Defects

Non-Structural (Installations)

Legal basis

Law No. 6 of 2019, Art. 40(a)

Law No. 6 of 2019, Art. 40(b)

Coverage period

10 years

1 year

Clock starts

Completion certificate date

Handover date (or completion certificate if possession is delayed)

What's covered

Foundation, columns, beams, slabs, load-bearing walls

Electrical, plumbing, sewerage/drainage, mechanical installations

Typical examples

Structural cracking, settlement, structural waterproofing failure

Leaking pipes, faulty sockets, AC drainage, water heater faults

Who pays to fix it

Developer, at no cost to the owner

Developer, at no cost to the owner


What Counts as a Structural Defect

  • Cracks in load-bearing walls, columns, or beams that go beyond surface plaster

  • Foundation settlement causing doors, windows, or floors to go out of level

  • Roof or podium waterproofing failures that let water into the structure itself

  • Corrosion-driven concrete spalling (exposed, rusting rebar)


What Counts as a Non-Structural (Installation) Defect

  • Electrical sockets, switches, or distribution boards that don't work or trip

  • Plumbing leaks at joints, faucets, or under sinks

  • AC units that don't cool properly or drain incorrectly

  • Sewerage and drainage blockages or slow drains

  • Water heater or boiler faults


From the Field

Picture a buyer who takes handover of a two-bedroom apartment in Dubai Hills Estate in January. Eight months later, the kitchen tap starts leaking under the sink, and the main bedroom's AC unit stops draining properly, soaking the carpet. She assumes "the ten-year warranty" covers it and doesn't rush to report it. By the time she writes to the developer in month thirteen, the one-year window for installation defects has already closed — the leak and the AC fault were never structural, so the ten-year clock never applied to them. A snagging inspection booked in month eleven instead of month thirteen would have caught both issues while the developer was still obligated to fix them for free.


Why the One-Year Window Is the One to Watch

The ten-year structural warranty sounds reassuring, but it covers a narrow category of serious, often rare defects. Most of what a snagging inspection actually finds — loose tiles, paint defects, electrical faults, plumbing leaks, AC performance issues — falls under the one-year installation window, not the ten-year structural one. The most useful time to document defects is early: right at handover, and again in the months that follow, well before month twelve.


Common Mistakes Buyers Make

  • Assuming the ten-year structural warranty also covers electrical and plumbing issues

  • Reporting defects verbally or over WhatsApp instead of in writing, with no dated record

  • Waiting until month ten or eleven to book a follow-up inspection, leaving no time to escalate before the window closes

  • Not keeping photos, videos, or a signed snagging report as evidence

  • Assuming a resale purchase restarts the one-year clock — it doesn't


Defect liability periods and their exact starting dates can be affected by your specific sale and purchase agreement, the project's completion certificate date, and any delay in taking possession — confirm the wording in your own contract, or with a legal advisor, before relying on these timelines for a claim.


If a developer is slow to respond once you've reported a defect, our guide on what to do about snagging after handover walks through how to escalate. We've also written about the transparency buyers deserve from whoever inspects their unit, and about why professional snagging protects developers too, not just buyers — which is part of why timely, well-documented inspections matter to both sides.


Frequently Asked Questions

No. The one-year period runs once, from handover (or from the completion certificate if you delayed taking possession), regardless of how many repairs happen within it. A developer fixing one issue in month three doesn't restart the clock for a different defect you discover in month eleven.

No. Both periods are tied to the project's original handover and completion certificate dates, not to your purchase date. Buy a resale unit nine years after handover and you may have only months left on the structural warranty and none left on the installation window.

No law in Dubai makes a snagging inspection compulsory. It's a safeguard buyers choose because the installation window is short, and a dated, documented report holds up far better than a verbal complaint if a dispute arises.

Usually not. Hairline or cosmetic cracking in plaster and paint is normally treated as a non-structural issue under the shorter one-year window, unless an engineer confirms the crack reflects an underlying structural problem.

The developer, first. Report the defect in writing within the applicable period and keep a dated record of that submission. The Dubai Land Department only becomes relevant if the developer fails to respond or refuses a valid claim.


Two different clocks, two very different sets of defects — and only one of them is actually running out fast. Treat your first year in a new Dubai property as the window that counts most, and you'll catch the small, fixable issues before they become expensive ones.

Buying or receiving your keys soon? Get your snagging inspection before you sign. RAMI Property Inspections & Snagging is the snagging company Dubai buyers trust to put every installation issue on paper while the developer is still obligated to fix it for free.

  • Call/WhatsApp: +971552466250

  • Email: ops@ramipropertyinspections.com

  • Visit Us: Al Barsha 1, Dubai, UAE

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.

R A M I TECHNICAL SERVICES CONTRACTING L.L.C  © 2025 All Rights Reserved

 
bottom of page