Re-Snagging in Dubai: Checking the Developer's Fixes

Writer: RAMI
RAMI
5 days ago
5 min read

When a Dubai developer says the items on your snag list are fixed, a re-snagging inspection in Dubai is the only reliable way to confirm it: a second visit that rechecks every item on your original report against what was actually done, then flags anything still wrong or newly damaged during the repair work.

It happens once the developer notifies you that remedial works are complete, usually a few weeks to a couple of months after the first snagging report, and it covers the same rooms and the same defect list rather than a fresh walkthrough. A proper re-snagging visit also tests repairs instead of just looking at them: taps are run, doors are cycled, sealant is checked for cure, and touched-up paint is inspected under raking light for the texture mismatches a quick glance misses.


What a Re-Snagging Visit Actually Checks

  • Every defect from your original snagging report, matched item by item against the repair notes

  • Whether the repair fixed the cause, not just the symptom — resealing a leak, not just repainting the stain it left

  • New defects introduced during the repair work itself: scuffed walls, chipped tiles, disconnected fittings

  • Areas the contractor worked near but wasn't asked to touch

  • Photographic proof matched side by side against the original snagging photos


How Long Should You Wait Before Booking It?

There's no single legally mandated repair window in Dubai for routine snags — timing runs on your sale and purchase agreement and how much work the list involves, not a fixed clock. What is regulated is how long the developer stays on the hook once you've accepted the unit. Under Law No. 6 of 2019 on Jointly Owned Property, Article 40 gives owners a 10-year window for structural defects in the jointly owned building, and a separate 1-year window from handover to have mechanical, electrical, sanitary and similar installations repaired or replaced — the period most routine snag-list items fall under. We break down what each window actually covers in our guide to Dubai's defects liability period.

In practice, the repair-and-recheck cycle for routine items — paint, sealant, fittings, minor tile work — moves faster than either legal window: commonly 2 to 6 weeks for the developer to action the list, then another 1 to 2 weeks before the re-visit is scheduled. Timelines vary by developer workload, payment plan and the scope of your original snag list, so confirm repair deadlines against your own sale and purchase agreement rather than a general rule.


From the Field

Illustrative example: on a re-snagging visit in a Dubai Hills Estate villa, an upstairs bathroom leak had been "fixed" by repainting the ceiling stain in the room below — the grout failure in the shower tray above was never opened up. The stain was back within three weeks. It's a pattern re-snagging exists to catch: a visible symptom gets patched while the actual defect, often hidden behind tiling or under flooring, is never corrected.


First Snagging vs. Re-Snagging

Aspect

First Snagging

Re-Snagging

Purpose

Identify every defect before handover

Verify each identified defect was actually corrected

Timing

Before or at handover

After the developer reports repairs complete

Scope

Whole unit, every system and finish

The original snag list, plus areas the repair crew touched

Typical duration

2-4 hours for an apartment, longer for a villa

30-90 minutes, scoped to the outstanding items

Who should attend

Buyer or their inspector

Ideally the same inspector, for a direct before/after comparison

Common finding

Unfinished trades, cosmetic defects, system faults

Cosmetic cover-ups over unresolved root causes


Common Mistakes When Accepting Developer Repairs

  • Accepting a WhatsApp photo from the contractor as proof a defect is resolved

  • Signing the handover clearance form before the re-visit actually happens

  • Assuming a repainted or recaulked surface means the underlying cause was fixed

  • Skipping a re-test of water pressure, drainage and electrical circuits after "repairs"

  • Not comparing against the original snag-list photos, room by room

  • Letting the contractor who caused the defect be the only one who signs it off as resolved


What If the Second Visit Still Finds Defects?

Put the outstanding items back to the developer in writing, referencing the original snag-list item numbers so there's no ambiguity about what's still open. If the item falls inside the 1-year installations window or the 10-year structural window under Law No. 6 of 2019, say so explicitly in the notice — it puts the developer's obligation on the record. For a wider look at what to do once you're past handover with defects still open, see our guide on snagging in Dubai after handover. If repairs stall entirely, RERA's dispute-resolution channels and the Dubai courts remain available as a last resort; legal costs and outcomes vary case by case, so this is general information, not legal advice.


Re-snagging is the step most buyers skip because it feels like the hard part is already behind them. It isn't a formality — it's the only check that tells you whether the fix actually worked. For the full process from first inspection through handover, our complete guide to property snagging in Dubai for buyers walks through every stage in order.

Buying or receiving your keys soon? Get your snagging inspection before you sign — and if the developer's fixes are already underway, a property snagging dubai re-check from RAMI Property Inspections & Snagging, Dubai's property inspection and snagging company, confirms they hold up before you sign off.

  • Call/WhatsApp: +971552466250

  • Email: ops@ramipropertyinspections.com

  • Visit Us: Al Barsha 1, Dubai, UAE


If you're using the same inspection company for the follow-up visit, most charge a reduced re-inspection fee rather than the full first-visit rate, since the scope is limited to outstanding items. Ask your inspector about this before booking the first report, as policies vary by company.

You can decline to sign a clearance or snagging sign-off until the items you flagged are actually resolved, but this doesn't stop separate handover steps like key collection under some contracts. Check the specific wording in your sale and purchase agreement, since developer practices differ.

It isn't mandatory, but using the same inspector for the re-snagging visit makes the before-and-after comparison far more reliable, since they already know exactly what each flagged item looked like the first time.

There's no fixed legal cap on re-inspection requests for the same defect while it remains within the applicable liability window. In practice, most items are resolved within one or two rounds of repairs; a defect that keeps recurring after that is worth escalating in writing.

Notify the developer in writing before the 1-year window under Article 40(b) of Law No. 6 of 2019 closes, since a documented complaint made within the period is what preserves your claim. Once a defect is formally raised in time, resolving it can continue past the deadline.

Yes — on a resale, there's no developer repair obligation to fall back on, so a follow-up visit after the seller fixes agreed items is really a private re-check between buyer and seller, not a warranty-backed process the way new handovers are.